Saturday, May 1, 2010

Progress Report Till 扩建新校舍之进展报告 09/02/2010

23/11/09 – 04/12/09
Piling

3/12/09
Footing Pile Cap

08/12/09
Concreting Footing

11/12/09
Back Fill Pile Cap

16/12/09
Concreting Footing

18/12/09
Back Fill Pile Cap

22/12/09
Concreting Ground Beam

29/12/09
Concreting Ground Floor Slab

01/01/10
Concreting Ground Floor Column

02/01/10
1st Floor Slab & Beam Form Work

14/01/10
Concreting 1st Floor Slab and Beam

15/01/10
1st Floor Slab & Column Rebar & Framework

16/01/10
Concreting 1st Floor Slab & Beam

19/01/10
Concreting 1st Floor Column

武吉丁雅Bukit Tengah明和企业报效扩建新校舍所需要的全部粗沙和幼沙

福成旺砖厂槟隆厂砖厂有限公司万发厂砖厂有限公司报效部分红砖


25/01/10
Supply Red bricks 16 pallet x 660 pcs

01/02/10
Supply Red bricks 50 pallet x 600 pcs

04/02/10
Concreting 2nd Floor Slab & Beam

09/20/10
Concreting 2nd Floor Column